FER X Final: the new rules for incentives for plants up to 1 MW are operational

|

Emma Potter

Constraints on starting work

The direct access procedure is reserved for plants powered by renewable sources with a nominal power equal to or less than 1 MW belonging to the photovoltaic, wind, hydroelectric types (on aqueduct or not on aqueduct) and gas plants residual from purification processes. New construction, upgrading and renovation interventions fall within the scope.

In terms of time, for plants up to 1 MW access is permitted provided that:

  • the construction works were started after 7 August 2026 (date of entry into force of Ministerial Decree 18 June 2026, n. 194);
  • entry into operation will take place by 31 December 2030, unless the 10 GW quota is exhausted early (in which case the GSE publishes a notice granting a 60-day window for sending the last applications).

The start of work means the first of the following two dates:

  • actual start date of the construction works relating to the investment (understood as the formal communication of the start of works sent to the competent administration or the first material construction site act, excluding preparatory works);
  • date of the first legally binding commitment to order equipment or any other commitment that makes the investment irreversible (e.g. signing of a binding module/turbine supply contract or definitive purchase order).

On the other hand, if the intervention concerns a renovation of a plant that already benefits or has benefited from other incentives, the equipment orders and legally binding commitments can be undertaken even before the expiry or waiver of the old incentives (it being understood that the reference date for the Definitive RES X remains after 7 August 2026).

Application deadlines

Plants up to 1 MW have direct access without going through competitive procedures, by submitting the communication of entry into operation via the GSE IT portal following completion of the works. The standard contract establishes two peremptory deadlines calculated starting from the date of entry into operation recorded on Terna’s GAUDÌ system, in compliance with the following terms:

  • the communication of entry into operation must be sent within 90 days to obtain the incentive from the first day of operation;
  • if sent after 90 days, you will lose the right to the tariff for the entire period between entry into operation and the date of receipt of the late communication, but you will still be able to access it.

Once the threshold of six months from the date registered on GAUDÌ has been exceeded, it is no longer possible to request the incentive.

All-inclusive or differential rate

The period of recognition of the hammer price lasts 20 years. The delivery methods vary based on the size of the system:

  • for systems with a power of less than 200 kW it is possible to choose between the All-inclusive Tariff (TO), with direct withdrawal of energy by the GSE, and the Differential mechanism (two-way contract), in which the producer independently sells the energy on the market and the GSE provides or adjusts the difference compared to the Day Ahead Market price;
  • for systems with a power equal to or greater than 200 kW, exclusively the Differential regime applies.

The choice made when communicating entry into operation is irrevocable and cannot be changed over the course of twenty years.

The determination of prices is delegated by the Ministerial Decree of 18 June 2026 to a specific resolution of ARERA. In the previous transitional regime (resolution 339/2025/R/efr) for photovoltaics, in the transitional regime ARERA had set a basic tariff of 77 euros/MWh for direct access up to 1 MW, increased by 4 euros/MWh in the Central regions and by 10 euros/MWh in the North.

The specific increases to the award price remain confirmed: +27 euros/MWh for photovoltaic systems installed to replace asbestos or asbestos roofing (reproportioned based on the ratio between reclaimed surface and module surface) and +10 euros/MWh for photovoltaic systems on bodies of water. The Operational Rules also specify that prices are indexed 100% to inflation until the date of entry into operation, while during the twenty years of the contract a partial revaluation linked to operating costs is applied (20% for photovoltaic, 23% for floating photovoltaic and 17% for wind

Incentives and cumulation

On the cumulation front, the FER

  • capital contributions (allowed only for new construction projects);
  • guarantee funds and revolving funds;
  • tax breaks in the form of tax credit or tax relief from business income for investments in machinery and equipment.

Access to FER

Summary table: operating rules for direct access to the RES X Definitive

Scope of intervention

FER Operational Rule X Final (Part C)

Constraint or deadline

Power threshold

Systems with nominal power equal to or less than 1 MW

Also check the cumulative power of systems attributable to the same entity

Allowed technologies

Photovoltaic, wind, hydroelectric, purification gas

New construction, expansion and renovation permitted; mandatory ex ante and ex post DNSH compliance

Time window

Works started after 7 August 2026 and entry into operation by 31 December 2030

Quota at 10 GW; in case of early exhaustion, 60 days from the GSE notice

Application submission deadlines

Communication of entry into operation on the GSE portal within 90 days of the GAUDÌ date

Over 90 days loss of late fee; beyond 180 days definitive forfeiture of the right

Tariff regime

Under 200 kW choice between All-inclusive and Differential Tariff; from 200 kW to 1 MW Differential only

Irrevocable choice for 20 years; with zero or negative MGP prices Differential suspension without MBR

Cumulability

Can be combined with a single measure (capital account only for new construction, guarantee funds, tax credits)

Maximum ceiling of 40% of the investment cost; automatic cancellation of RID or SSP contracts

Read and download the Decree of 11 November and the operating rules here