Léon Grosse wins the Guyancourt station project at 29 million euros

|

Emma Potter

Grand Paris Express: Léon Grosse will build the Guyancourt station

Winner of a 29 million euro contract for the Société des Grands Projets, Léon Grosse Construction will carry out the structural work, the covered enclosure and the main developments of the future Guyancourt station.

Publi-Information

There Société des Grands Projets has retained Léon Grosse Construction to carry out the development work at Guyancourt stationon the line 18 of the Grand Paris Expressin Yvelines. Worth 29 million euros, this contract covers the structural work, the covered enclosure and the main developments of this new transport infrastructure, delivery of which is expected in the fourth quarter of 2030.

For the construction groupthis operation is part of the continuity of several projects carried out for the Société des Grands Projetsincluding the Maison Blanche station, on line 14, and the rear Noisy-Champs station, on line 15. In Guyancourt, the teams will have to deal with a particularly constrained technical environment, where coordination between the different markets and stakeholders will have a direct impact on the progress of the work.

A station with generous volumes

The architectural project was entrusted to Dietmar Feichtinger Architectes, within the ICARE project management groupwho has already worked on several stations and infrastructures of lines 17 and 18imagined a building combining a wooden and metal frame, large interior volumes and an exposed concrete structure.

The substantial ceiling heights will help to give scale to the spaces, while the curtain wall facades will constitute one of the architectural signatures of the work. The station will also host a monumental work of art, designed as part of the artistic program of the Grand Paris Express.

The future infrastructure is part of the second phase of line 18, which will link Christ de Saclay to Versailles-Chantiers. Ultimately, the complete line will have ten new stations, including three underground in this second phase, and should accommodate 110,000 travelers per day by 2030. © YouTube video Société des grands Projets

Multiple interfaces

Beyond the architectural characteristics, the Guyancourt construction site presents an organizational challenge since Léon Grosse Construction will have to intervene in an environment where many markets and companies coexist, with operations that will progress in close coordination.

The management of interfaces will be decisive in order to meet the various project deadlines. The teams will have to vacate the spaces on the planned dates, ensure the continuity of interventions and avoid any disruption to the deployment of the line’s future systems. Control of the schedule will therefore be based on precise management of the work and permanent coordination with the other players in the operation.

“This particularly technical project illustrates Léon Grosse Construction’s ability to support its clients in carrying out complex operations. This station represents an architectural, logistical and organizational challenge, which requires a global vision of the project and close collaboration with its various stakeholders. We are proud to support the Société des Grands Projets in carrying out this structuring operation for the region.” explains Sylvain Prosperi, the IDF Major Projects director of Léon Grosse Construction.

Sylvain Prosperi, the IDF Major Projects director of Léon Grosse Construction, here in the photo, notably manages the group’s complex operations in Île-de-France, including the construction site of the future Guyancourt station on line 18 of the Grand Paris Express. © Léon Grosse Construction

Low carbon concrete, recycled steel and 13,335 hours of insertion

The market also integrates several social, economic and environmental commitments. Thus, the project plans 13,335 hours of professional integration, intended to promote access to employment, while SMEs will also occupy an important place in the operation, with a share representing 42% of the cost of the work.

On an environmental level, several provisions should help limit the carbon footprint of construction, with the program notably providing for the use of low-carbon concrete and recycled steel. The teams will also seek to optimize the volumes of concrete by using, to carry out the refills, lost formwork pads which will limit the quantities of materials necessary.

A project until 2029

The start of work is scheduled for the end of 2026, and construction of the work must be completed in 2029, a deadline which will then allow testing of the rail systems to begin. There final delivery from Guyancourt station is planned for the fourth quarter of 2030.

The development contract, worth 29 million euros, is placed under the project management of the Société des grands Projetsassisted by LINK. The architectural project management is ensured by Dietmar Feichtinger Architectes, while the ICARE group, made up of INGEROP, ARTELIA and ARCADIS, is involved in the infrastructure. EGIS ensures project management of the systems.