A construction site in rhythm with the school calendar
Before the intervention, the energy diagnosis placed the school in class D. The walls and the attic were without insulation, the windows and doors had no thermal break and the heating plant had reached the end of its life.
The Municipality started the redevelopment with regional funding from the Recap tender, supported by the European ERDF 2021–2027 funds. The project, signed by engineers Ombretta Alcini and Manuele Giovanola of the Eleev studio, who also oversaw the construction management, involved the use of two insulators of different thicknesses, chosen according to the characteristics of the facades and in compliance with the Minimum Environmental Criteria (CAM).
Construction started in May 2026 and the official inauguration was held on 12 September. A few days early, the nursery school children had already been able to enter the classrooms, while on September 14th the doors opened for primary school students. To respect these dates, the ICETSrl company of Tromello (PV) brought forward some work compared to the program and updated the process from month to month.
The distinction between internal works, concentrated during the period of suspension of lessons, and external finishes, compatible with the resumption of teaching activities in conditions of separation from the construction site, represented a decisive element in the planning of the intervention: “We concentrated the work inside the school in the months without lessons, while the last external finishes were completed when the school was open, always separating the construction site from the areas used by the children”says Dr. Lavezzi of ICETSrl
In the same period, some works requested by the Municipality during construction were also included, including painting, railings and small restorations. The intervention also involved the attic, the windows, the tinsmithery and the external arrangements, as well as the renovation of the corridors, stairwell and refectory.

Graphited EPS and PIR coat: materials and thicknesses compared
A RÖFIX coat with RÖFIX EPS-F 031 GRAY panel in EPS with graphite additive, 120 mm thick and with a thermal conductivity of 0.031 W/(m·K) was installed on approximately 950 square metres.
In places where the available space required a more limited thickness, for a total surface area of approximately 90 square metres, 80 mm RÖFIX Purwall PIR panels were used.
The use of different insulating materials within the same intervention responds to the need to reconcile the thermal performance of the envelope with the geometric constraints of the existing building. In the presence of limited spaces, the use of insulation with low thermal conductivity allows the thickness of the insulation system to be limited.
At the base of the facades, a specific EPS was used for the plinth, which is more resistant to water and mechanical stress, while the attic was insulated with 20 centimeters of mineral wool.



Coating and windows: the issue of thermal bridges
“The connection between the coat and the new windows was one of the most delicate steps”explains Dr. Lavezzi. “The insulation had to turn up on the shoulders to limit thermal bridges and connect to the new stone windowsills with drip tray. The sequence was organized facade by facade, from the replacement of the windows to the installation of the insulating shoulders and the cladding, up to the window sills, the tinsmithery and the reinforced leveling”.
In the redevelopment interventions of the existing building, the connection between the external insulation system and the windows represents a particularly significant design and executive node. The continuity of the insulating layer at the openings helps to limit localized heat losses and reduce the risk of low internal surface temperatures.
During site inspections, the RÖFIX technician Luca Salamanca and Alessandro Zoppini of Emmezeta, the company’s reference dealer, provided technical instructions for the installation.
Summer and winter thermal comfort
The choice to work together on the walls, attic and windows becomes important even in the hottest months, when the temperatures in the classrooms can make the last weeks of lessons and the return in September tiring. “The coat is not only useful in winter: in general it keeps the temperature in the rooms more stable in all seasons“, observes Lavezzi.
However, the summer comfort of school environments does not depend only on the insulation of the opaque walls: it must also be evaluated considering the solar gains through the glass surfaces, the effectiveness of the shielding, the internal thermal loads and the ventilation methods. Hence the importance of an integrated approach to the redevelopment of the building envelope and systems.
As part of the intervention at the A. Bordoni school, the insulation of the facades was in fact combined with windows with selective glass and insulated roller shutters, while the overall project also includes mechanical ventilation for air exchange.
From class D to objective A2: energy performance and consumption
The transition from energy class D to A2 is the objective envisaged at the conclusion of the entire redevelopment project, which also includes a new heat pump, room-by-room temperature regulation and a 10.66 kWp photovoltaic system.
To compare actual consumption, we will wait for the conclusion of the first complete heating season, in spring 2027. Post-intervention monitoring represents an important step to evaluate the effectiveness of the solutions adopted, taking into account the climatic conditions and the actual methods of use of the school building.


Redeveloping school buildings: the role of planning and timetables
Meanwhile, the return of the classrooms for the start of lessons and the precise timing with which the project was carried out show how important the decisions made before erecting the scaffolding are in a school building project. The Dr. Lavezzi particularly underlines the importance of a realistic timetable built around the school calendar and of continuous dialogue between the Municipality, planners and the company, with rapid decisions on variations.
Intervening on the energy performance of school buildings means not only pursuing a reduction in consumption, but also improving the quality of the environments intended for teaching. An objective that places the comfort of students and teachers at the center of design choices, because the level of attention of students and the success of their learning path also depend on the well-being felt within the school environment.